pic1 pic1 pic1 pic1

Ongoing Projects

S.No.

Name of work

Approx. Cost

(in lacs)

Remarks

1

Const. of PWD Public Health office building at Nabha Road, Patiala.

2500.00

The works is under progress and likely to be completed by 15.05.2013.

2

Const. of 16 No. quarters Near PWD Public Health Head office building at Nabha Road, Patiala.

233.59

The works is under progress and likely to be completed by 31.05.2013.

3

Const. of Public Toilet & Canteen Near Tehsil Complex in Hira Enclave at Nabha.

34.27

The works is under progress and likely to be completed by 31.05.2013.

4

Dev. of Main park in Hira Enclave at Nabha.

50.68

The works is under progress and likely to be completed by 27.04.2013.

 

S.No.

Name of work

Approx. Cost

(in lacs)

Remarks

1.

Const. of Distt. Library at Nabha.

81.40

The works is under progress and likely to be completed by 31.05.2013.

2.

Const. of Cremation Ground Near Village Theri in Urban Estate, Phase-1 at Patiala.

67.48

The works is under progress and likely to be completed by 31.05.2013.

3.

Repair of internal Roads of 4, 5, 6 Merla plots in Urban Estate, Phase-2, Part-2 at Patiala.

33.20

The works is under progress and likely to be completed by 25.05.2013.

4.

Dev. of Commercial Complex in Phase-2, Part-2 at Patiala.

250.00

The works is under progress and likely to be completed by 20.07.2013.

5.

Dev. of PRTC site (3.65 Acre) Nabha Road at Patiala.

190.84

The works is under progress and likely to be completed by 2.10.2013.